• On our way to looking like the images above...
    Here’s where we’re at now! Click the + to see more!

    Lobby area:

    The old secretary room has been completely removed

    Brick has been cleaned

    Drop ceiling has been redone

    Walls have been patched and painted

    Office door has been painted

    Carpet fixed - until new carpet can be installed


    Welcome Center / Kitchen:

    We have a doorway from the Welcome Center into the Kitchen

    The two old rooms have been removed

    The double door jamb between the lobby and Welcome Center has been removed


    Family Room:

    The walls have been removed


    Storage Room:

    The wall separating the East and West rooms has been removed so there is just one large room for storage

  • LifeKids Area

    West Room:

    The wall creating 2 rooms from the 1 original room has been removed.

    Cords and cables have been secured

    Carpet has been cleaned

    A projector has been mounted

    Tables have been purchased and installed

    Drop Ceiling has been completed


    Middle Room:

    The wall creating 2 rooms from the 1 original room has been removed

    Cords and cables have been secured

    Carpet has been cleaned

    Drop Ceiling is nearly completed


    East Room:

    Tables have been purchased and installed

    Chairs have been acquired

    Games and toys have been cleaned and are in use

  • Building:

    Office:

    Cox fiber internet has been installed and is functional

    Installed new server hardware

    Installed new security cameras

    Installed new WiFi access points in key areas throughout the building

    Computers and Copier are now connected to the intranet and are functional


    Auditorium:

    We have added stage lights to help with light control and comfort

    We have connected the system to the internet

    2 65” TV’s have been installed and connected and are working

    Brand new seating installed and in use

    Walls have been painted

    Laminated beams have been stained to 12’



    Exterior:

    Courtyard work continues

    Chainlink fencing along the West and South of the property has been removed

    New sign is installed and functional (Thank you to Steve and Tammy Allen of Allen’s Signs and Lighting for donating their labor and materials for this project!)

    Exterior painting is nearly complete